OERC Agrees to Public Hearing on Vedanta Power Tariff After Objection

OERC Orders Public Hearing on Vedanta Tariff After 10-Year Gap; Anand Mahapatra Raises Legal Objection Over Consumer Interests

0

In a significant development concerning Odisha’s power sector, the Odisha Electricity Regulatory Commission (OERC) has agreed to conduct a public hearing on Vedanta’s power tariff determination after objections were raised over the absence of public consultation for nearly a decade.

The issue came up during a tariff hearing held by OERC on November 17, concerning Vedanta’s Multi-Year Tariff (MYT) petition for the period 2024-25 to 2028-29 and its true-up tariff applications for 2019-20 to 2023-24.

Energy analyst Anand Mahapatra strongly opposed the proceedings through an affidavit, arguing that fixing Vedanta’s power tariff without a public hearing for the past ten years was illegal. Citing Section 64 of the Electricity Act, 2003, he maintained that the commission must invite public participation and consider consumers’ views before determining electricity tariffs.

Mahapatra pointed out that Vedanta operates a 2,400 MW independent power plant (IPP), comprising four units of 600 MW each, in Jharsuguda district. Odisha is entitled to 720 MW from the plant. However, he alleged that Vedanta has been supplying only around 400 MW to GRIDCO, while utilising the remaining power for its own aluminium smelter operations.

According to him, the reduced availability of Odisha’s entitled power has forced the state to procure electricity from other sources, contributing to higher power costs for consumers.

He also questioned why OERC conducts public hearings for tariff determination of Odisha Power Generation Corporation (OPGC) but has not followed the same procedure in Vedanta’s case.

Taking note of the objections, the two-member OERC bench, comprising Acting Chairperson Biswajit Mohanty and member Sudhanshu Bada Panda, sought the views of Vedanta and GRIDCO. Both parties reportedly supported holding a public hearing.

The commission subsequently directed its secretary to issue a public notice to facilitate the hearing.

Meanwhile, under its wholesale power tariff order notified on March 24, 2026, OERC has directed Vedanta to supply Odisha’s entire 720 MW entitlement, equivalent to 5,037 million units, to GRIDCO at Rs 2.77 per unit for the current year.